GRP sectional water tanks are assembled on site from hot-pressed glass-reinforced polyester panels measuring 1 × 1 m. They cover capacities from 1 to over 500 m³ at heights of 1.0 to 5.0 m, with a design life of over 25 years. Al-Asas Al-Thameen handles design, supply, installation, testing and commissioning in Libya, Jordan and Algeria.

Why a GRP Sectional Tank Instead of Steel or Concrete?

  • Fits through any door. Panels ship flat — a 100 m³ tank takes up a small fraction of the volume of a welded steel tank, and can be brought onto a roof or into a basement that no pre-built tank could reach.
  • Bolted by hand, no welding. Panels are bolted together on site — no crane and no welder needed.
  • No rust, no painting. No cathodic protection, and no internal lining that peels off after a few years.
  • Thermally insulating. A GRP shell keeps water cooler than steel or concrete through the Libyan summer.
  • Expandable and relocatable. Panels can be added to increase capacity, or the tank can be dismantled and rebuilt at another site.
  • All wetted parts are suitable for drinking water — GRP panels, SS 316 stays and bolts, and non-toxic PVC foam sealant.

Read the details and animated diagrams in our guide: Benefits of GRP water tanks, from the University of Benghazi project.

Applications

Materials of Construction

Component Material Specification
Wall, base and roof panels Hot-pressed GRP 1000 × 1000 mm module — thickness graded by hydrostatic pressure
Panel sealant Closed-cell PVC foam 75 × 3 mm and 150 × 3 mm — non-toxic
Bolts, nuts and washers Stainless steel 316 M10 / M12 — plastic-capped on the wetted side
Internal stays Stainless steel 316 12 mm diameter — 1.0 to 5.0 m with SS 316 brackets
External reinforcement Hot-dip galvanized steel or SS 316 Flat bar 40×3 and 80×3 mm — corner angle 75×75 mm
Roof supports Pultruded FRP 50 × 50 mm — 1.0 to 4.0 m
Nozzles and flanges Cast polyester Inlet · outlet · drain · overflow — all standard sizes
Ladders Internal FRP · external galvanized 1.0 to 4.0 m in 0.5 m steps

Capacity Table (m³)

Total nominal volume = length × width × height. Allow about 5% freeboard to arrive at the actual working volume. Any size is possible in one-meter increments — the table shows the most common sizes.

Footprint
L × W (m)
H=1m H=1.5m H=2m H=2.5m H=3m H=3.5m H=4m
2 × 1 2.0 3.0 4.0 5.0 6.0 7.0 8.0
2 × 2 4.0 6.0 8.0 10.0 12.0 14.0 16.0
3 × 2 6.0 9.0 12.0 15.0 18.0 21.0 24.0
3 × 3 9.0 13.5 18.0 22.5 27.0 31.5 36.0
4 × 3 12.0 18.0 24.0 30.0 36.0 42.0 48.0
4 × 4 16.0 24.0 32.0 40.0 48.0 56.0 64.0
5 × 4 20.0 30.0 40.0 50.0 60.0 70.0 80.0
6 × 4 24.0 36.0 48.0 60.0 72.0 84.0 96.0
6 × 5 30.0 45.0 60.0 75.0 90.0 105.0 120.0
8 × 4 32.0 48.0 64.0 80.0 96.0 112.0 128.0
8 × 5 40.0 60.0 80.0 100.0 120.0 140.0 160.0
10 × 5 50.0 75.0 100.0 125.0 150.0 175.0 200.0

Heights of 4.5 and 5.0 m are available; they require additional external reinforcement and a heavier base, and are quoted per project.

Available Accessories

Accessory Material Size / Range
Internal ladder FRP / GRP 1.0 – 4.0 m in 0.5 m steps
External ladder Galvanized steel With safety cage on request
Water level indicator Aluminum / PC / stainless steel 1.5 – 4.0 m — external float with direct reading
Air vent PVC DN50 / DN100 — with insect-proof mesh cap
Manhole and cover GRP 600 × 600 mm — lockable with raised rim
Roof supports Pultruded FRP 1.0 – 4.0 m — for wide spans

Foundation & Installation Requirements

Concrete Foundation

  • Continuous reinforced-concrete plinths or a steel frame beneath every panel joint line, i.e. every one meter.
  • Top-surface levelness within 2 mm per meter and 6 mm over any 6 meters — measured both across and diagonally.
  • The structural adequacy of the foundation and its design loads are the client’s responsibility.
  • Foundation drawings for the selected size are issued with the purchase order.

Clearances

  • Leave at least 600 mm on all sides around the tank and 600 mm above it, measured from the external dimensions.
  • This space must remain clear after installation for inspection and maintenance.
  • If the tank roof is 2.5 m or more above finished floor level, allow space for a ladder tower.

Certifications & Standards

Panels are manufactured to Al-Asas Al-Thameen’s specification at approved factories and comply with the standards and approvals below. Certificates are issued in the name of the producing factory — valid original copies are included in every project file.

Standard Details
BS 6920-1:2014
Suitability for contact with drinking water
The British Standard for the suitability of materials in contact with drinking water. Panels are tested and passed for: odor and taste, appearance, growth of aquatic microorganisms, extraction of substances, and extraction of metals.
WRAS Approved Material
UK Water Regulations Approval Scheme
GRP water tank panels approved under the UK Water Regulations Approval Scheme for materials in contact with drinking water, with a current approval.
TSE K 304
Turkish Standards Institution
Certificate of conformity for standard water tanks intended for drinking water and general use.
ISO 9001:2015
Quality management system
The producing factory holds a quality management system certification for the production and sale of standard metal and composite water tanks.

Warranty & Scope of Supply

Warranty: 12 months from delivery against manufacturing defects, provided the tank is installed on a foundation built to the issued drawings and operated within the stated design conditions.

Full scope of service: sizing · foundation drawings · supply · installation · hydrostatic load testing · disinfection · commissioning.

Frequently Asked Questions

Is a GRP tank suitable for drinking water?

Yes. All wetted parts are suitable for drinking water: GRP panels, SS 316 bolts plastic-capped on the inside, and non-toxic PVC foam sealant. The panels also hold the British BS 6920 and WRAS approvals for suitability in contact with drinking water.

How long does installation take?

It depends on capacity and how ready the foundation is. Small and medium tanks are installed within a few days once the foundation is complete. The foundation itself — the client’s responsibility — is usually the critical path in the schedule.

Can the tank capacity be increased later?

Yes, and this is one of the main advantages of the sectional system. Panels can be added to enlarge the tank, provided the foundation was designed or extended to carry the new capacity. The tank can also be fully dismantled and rebuilt at another site.

How does it compare with a welded steel tank?

A steel tank needs a crane and an access opening large enough for the whole tank, plus painting, rust protection and periodic lining maintenance. A GRP sectional tank arrives flat, is bolted together by hand, doesn’t rust or need painting, and insulates thermally — a real advantage in the Libyan summer.

Do you provide concrete foundation drawings?

Yes. The foundation drawing for the selected size is issued with the purchase order, and includes plinth locations and design loads.


Request a Quote for a GRP Tank

Tell us the capacity you need, the space available and the intended use — and we’ll recommend the right size, with the foundation drawing and full technical datasheet.